Realignment of
existing taxiway which included the removal of 8,800
square yards existing taxiway pavement; placement of
46,000 cubic yards embankment in new taxiway; 5,300
cubic yards suitable excavation adjacent; 17,000 tons of
P-401 pavement; weekend (20-hour period) closures; storm
drainage; lighting, signage and corresponding controls.

|