HIGHWAYS

 PROJECT GALLERY
 

 

 

Route 123 & Hooes Road
Fairfax, Virginia

Owner:   Virginia Department of Transportation
Contract Amount:   $19.8 Million
Completion Date:   May 2006
 
Construction of improvements to Route 123 expanding it to a 4-lane divided primary roadway. The project consisted of over 4-miles of both new roadway location and widening of existing roadways. In addition to extensive interface between Branch and adjacent business and residential property owners, the project included 700,000 cubic yards of excavation, almost 11,000 square feet of sound barrier walls, over 3,200 square feet of retaining structures, 6 signalized intersections a complete landscaping package.

During the course of the project, the originally planned sequence of traffic switches was greatly improved. These traffic sequence changes not only reduced the original number of project phases, but also helped in managing unanticipated impacts associated with over $3 million of water and sanitary sewer upgrades. This project was complete ahead of schedule.
 
Return to Project
Gallery Main Page